General Contractor Requirement-Set & Mandate Onboarding Template (Copy-Paste Checklist)

A requirement set is only useful if a subcontractor can read it and a reviewer can check it. This template gives you the trade matrix, the instruction wording, the CSV format and the alert schedule to onboard a trade without another email thread.

Mustafa Al-Saedi· Founder, RelyTiaPublished November 29, 2026Last updated November 29, 20266 min read

How to use this template

Work through the six steps in order. Each step produces something a subcontractor can act on or a reviewer can check. Skip a step and the requirement set becomes a wish list: everyone agrees it matters, nobody knows what to upload.

The template is generic on purpose. Replace the trade names, document names and instructions with what your contracts and local counsel actually require. Do not copy a US limit or a state licence requirement into a country where it does not apply.

Step 1: Build the trade matrix

Start with the trades you actually onboard, not the full list of trades that exist. For each trade, separate core documents that every subcontractor in that trade must provide from conditional documents that depend on scope, value or risk.

Trade requirement matrix example
TradeCore documentsConditional documentsOwner
ElectricalPublic liability, employers' liability, electrical competence registration, safety policyProject-specific additional insured wording, medium-voltage authorisationRegional compliance lead
MechanicalPublic liability, employers' liability, trade registration, safety policyGas registration, pressure-system competence, manufacturer certificationRegional compliance lead
General labourPublic liability, employers' liability, safety inductionWorker competence cards for site accessSite manager
RoofingPublic liability, employers' liability, working-at-height certification, safety policyScaffold competence, fall-arrest equipment inspectionHSE lead

Step 2: Write plain-language instructions

Every requirement needs three lines: what to upload, what the reviewer checks and what is not accepted. Write them for a person on a phone at a site office, not for a procurement manual.

  • Use the local name for the document, not your internal abbreviation.
  • State the legal entity that must be named on the evidence.
  • Name the issuing party, because an upload and an issuer confirmation are different evidence.
  • Say what happens at expiry, so the subcontractor knows the renewal deadline.
Copy-paste instruction block
Name: [the document name the subcontractor would recognise]
Upload: [exactly which file, which pages, and which fields must be visible]
Reviewer checks: [entity name, reference number, dates, and the issuing party]
Not accepted: [the substitutes that are commonly sent by mistake]
Expiry: [how the validity date is determined]

Step 3: Prepare the bulk CSV

Bulk onboarding is the difference between a pilot and a program. Keep the file to three columns so a project administrator can produce it from an existing vendor list without reformatting.

  • One row per legal entity, not per contact. Extra contacts belong in the record, not the invite file.
  • Use the trade names from the matrix so the correct requirement set is applied.
  • Keep the file at or below the 100-row limit RelyTia accepts for a bulk CSV invite.
  • Deduplicate before uploading; a second invite to the same entity creates noise, not coverage.
  • Check that every email address belongs to the company being invited.
Bulk invite format
company_name,contact_email,trade
Meridian Electrical Contractors,compliance@meridian.example,Electrical
Northline Mechanical,northline@example.com,Mechanical
Harbour Roofing,admin@harbour.example,Roofing

Step 4: Send single-use mandates and record acceptance

A mandate is an invitation with a boundary. RelyTia issues single-use links that expire after 30 days. Nothing is shared with the GC until the subcontractor accepts, and the acceptance itself is recorded with a timestamp.

That acceptance trail matters at audit time. It shows the requirement set the subcontractor was given, when they accepted it and which documents were requested. Without it, a dispute becomes a memory test.

Step 5: Set the expiry alert schedule

Compliance decays quietly. A document that was valid at onboarding can expire before the first draw. Use the same alert schedule for every trade and every region so escalation is predictable.

Expiry alert schedule
Days before expiryRecipientAction
30Subcontractor compliance contactRequest the renewal and confirm the expected date
14Subcontractor compliance contactEscalate to the account owner if no renewal is uploaded
7Subcontractor and GC compliance leadConfirm the document is in progress or flag a blocker
1GC compliance leadPrepare a named blocker for the project or draw
0 (expired)GC project and finance leadsThe item remains visible but no longer satisfies the requirement

Step 6: Decide the evidence label you need

Not every requirement deserves a broker confirmation. Identity documents, safety policies and tax registrations are typically self-reported. Certificates of insurance and surety bonds are the ones where a source confirmation changes the weight of the evidence.

Be explicit in the requirement set. If a certificate may be self-reported, say so. If the project requires Broker-confirmed evidence, say that too, and explain that the confirmation comes from the broker or issuer through a one-time code or an approval file, not from RelyTia.

Onboarding checklist

  • Trade matrix completed for every trade you onboard.
  • Instruction block written for each requirement.
  • CSV prepared with one row per legal entity.
  • Mandate link expiry and acceptance trail confirmed.
  • 30/14/7/1-day alert schedule assigned to named owners.
  • Evidence label decided per requirement.
  • Pilot run with one trade and one project.
  • Requirement wording reviewed by local counsel before it becomes contractual.

What not to put in a requirement set

  • A US dollar insurance limit copied into a country that does not use it.
  • An abbreviation the subcontractor will not recognise.
  • Personal data that the reviewer does not need to make a decision.
  • Legal conclusions such as 'must comply with all applicable law' with no reviewable document.
  • A document that the platform cannot label or expire, which becomes invisible after upload.
  • A requirement with no named owner, because nobody will chase it.

Rollout: one trade, one project, then scale

Pilot the requirement set with a single trade on a single project. Measure two things: how long the average subcontractor takes to complete the set, and how many documents come back rejected. High rejection rates usually mean the instructions are ambiguous, not that the subcontractors are careless.

Once one trade works, add the next. Keep the core requirements stable and let regional overlays carry the local differences. That way a new country does not require a new program, only a new overlay.

Frequently asked questions

What columns does the bulk CSV need?

RelyTia accepts company_name, contact_email and trade. Each row should be one legal entity, the trade must match the requirement matrix, and the file is limited to 100 rows per bulk invite.

How long do mandate links last?

Mandate links are single-use and expire after 30 days. Nothing is shared with the GC until the subcontractor accepts the mandate, and the acceptance is recorded with a timestamp.

When should a GC require Broker-confirmed evidence?

Use Broker-confirmed for certificates of insurance and surety bonds where the source matters to the approval decision. Identity, safety-policy and tax documents are usually sufficient as Self-reported evidence.

Does this template work outside the United States?

Yes, if you replace the trade names and document names with local equivalents. Keep the core requirements stable and add a country overlay for trade registration, labour evidence and local tax forms.